Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

AG Partners Feedmill Loadout Expansion

Ductile Iron Piles provided high capacity, low vibration pile option for foundation support immediately adjacent to existing facility.

Project Description:

Expansion of the existing Ag Partners Feedmill Facility involved the construction of a new 9-bay Loadout Bin structure. The new structure was located immediately adjacent to the existing Loadout Bin Building. A total of 20 columns with loads of up to 540 kips required support.

Geotechnical Details:

Soil conditions explored during a previous nearby expansion consisted of up to 20 feet of fill containing loose silty sand and soft silt and clay. The fill was underlain by weathered sandstone and weathered dolomite. One boring encountered a thin layer of glacial till between the fill and weathered rock. Drilling refusal on competent rockoccurred in all borings around 30 feet below grade. No groundwater was encountered.

Project Challenges:

Provide a high capacity, low vibration pile option for foundation support immediately adjacent to existing facility.

Advantages

  • Low vibration installation adjacent to existing building
  • Easily adapt to varying rock depths
  • High-capacity pile solution
  • Rapid installation

Design and Construction Solution

Based on the successful support of foundations for a prior expansion at the same facility, the design team planned to use Ductile Iron Piles for column support. Engineers at VAA and Ground Improvement Engineering arrived at a Ductile Iron Pile design solution. A Series 170/9.0 Ductile Iron Pile (170 mm outer diameter and 9.0 mm wallthickness) was selected to provide a working capacity of 80 tons (compression) for pile cap support. With 3 pile groups supporting each pile cap, a total of 60 Ductile Iron Pile locations were specified.

A Series 170/9.0 test pile was installed through soft soils and terminated by achieving “set” on rock at a depth of 25 feet. The pile was load tested to 160 tons (320 kips) to achieve 200% of the design load. The load test results showed nearly linear deflection to the maximum test load with 1.04 inches of total deflection. The test pile rebounded to 0.32 inch. Full-scale load test results confirmed the acceptable performance of the system to support the 80 ton design loads.

Production pile installation began on the opposite side of the site as the test pile location. Pile depths in this areaproved to be significantly deeper. Set was achieved on rock at depths upwards of 55 feet as the bearing layer dipped across the site. The unexpected deeper rock depths were easily handled with the Ductile Iron Pile’s Plug- and-Drive connection that allowed for rapid insertion of additional 5-meter modular pile sections with no delays in production. Termination depths of piles reduced as the crew moved across the site towards the original test pile location.

Even with the increased depth, the Ductile Iron Pile installations proceeded as planned. A total of 60 piles with lengths ranging from about 25 to 55 feet were installed in one week to make short work of the pile scope on the project.

 


Project Team Members

DIP Installation Partner: Peterson Contractors, Inc.

DIP Design Partner: Ground Improvement Engineering, Inc.

Geotechnical Engineer: Braun Intertec

Structural Engineer: VAA, LLC

General Contractor: Lodermeiers, Inc.

Project

AG PARTNERS FEEDMILL LOADOUT EXPANSION

Pile Type

END-BEARING DUCTILE IRON PILES

Location

Goodhue, MN

Challenges

Adjacent Structures
Vibrations

Case Study File

Download